Effective Load Carrying Capability for Limited Duration Resources and Intermittent Resources

PJM staff is bringing this issue forward for consideration based on two sources: 1) The Planning Committee has been discussing switching to an Effective Load Carrying Capability (ELCC) method to calculate the capability of wind and solar units in the capacity market. 2) In response to a paper hearing FERC initiated in Docket No. EL19-100 regarding the capability of energy storage resources, stakeholders have proposed, and PJM supports, switching to an ELCC method to calculate the capability of energy storage resources.

Issue Details

Issue Status: Emerging
Stakeholder Body: Capacity Capability Senior Task Force
Stakeholder Process Status: Approved
Issue Catalyst: PJM and FERC Docket No. EL19-100
Date Created: 3.26.2020
MC Approval Date:
Target Completion Date: 1.29.2021
Actual Completion Date:
FERC Filing(s): Yes
Agreement Change(s):
Manual Change(s): No
MC Annual Plan: 2020
Date Documents
7.9.2020 Meeting materials from the OC meeting
Item 8 - Capacity Capability Senior Task Force Update  PDF
Date Type Documents