Replacement Capacity

The Incremental Auction Senior Task Force was created to focus on reviewing the current PJM RPM Incremental Auction process and structure with specific focus on circumstances where PJM is a capacity seller. This group will review excess capacity sale and Incremental Auction practices and discuss whether modifications are required to the PJM Incremental Auction processes. This task force will report directly to the Markets and Reliability Committee.   A subsequent problem statement involving the potential long-term reliability impacts of speculative behavior as a result of current replacement capacity transaction business rules was approved by the MRC and assigned to the IASTF.

Proposed Timeline

Issue initiated: 3.23.2017
Work begins: 5.10.2017
Target Completion: 6.18.2020
Actual Completion: 1.19.2018

Issue Details

Stakeholder Body Incremental Auction Senior Task Force
Facilitator Chmielewski, Brian
Subject Matter Expert Scheidecker, Paul
Problem Statement/
Issue Charge First Read
2.23.2017
Issue Catalyst Neal Fitch, NRG; Bob O’Connell, Panda Power Funds
Issue Status Closed
Manual Changes No
Agreement Changes Open Access Transmission Tariff, Reliability Assurance Agreement
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • Completed Options
  • Completed Packages
  • Completed Consensus
  • Completed Review
  • Completed Completed