Capacity Markets: FRR Load Forecast Changes

This issue concerns allowing changes in load forecast to affect FRR Obligations. Proposed changes would modify the rules to the load forecasts of FRR entities to increase or decrease in the same manner as RPM LSEs.

Proposed Timeline

Issue initiated: 6.8.2009
Work begins: TBD
Target Completion: TBD
Actual Completion: TBD

Issue Details

Stakeholder Body Members Committee
Subject Matter Expert Bastian, Jeff
MC Approval Date 8.25.2009
Problem Statement/
Issue Charge First Read
6.8.2009
Issue Catalyst Member request
Issue Status Closed
Manual Changes No
Agreement Changes Open Access Transmission Tariff
  • Stakeholder Process Step

  • Completed Approved
  • Completed Education
  • Completed Interest
  • Completed Design
  • Completed Options
  • Completed Packages
  • Completed Consensus
  • Completed Review
  • Completed Completed