Stakeholders have determined they would like to review the following 3 items to determine if any changes to the use of the PLC in the Emergency DR nomination, measurement and verification and add back processes should be considered: 1) Customer PLC Risk - Customer wants to be fully interruptible but does not know their PLC three years in advance of Base Residual Auction (BRA) 2) PLC time lag - Customer load changes (growth or decline) are not incorporated in PLC until approximately one year later. 3) PLC alternatives - Review accuracy of, and potential alternatives to, PLC for the purpose of establishing the contribution of each customer level registered demand response resource to the PJM system reliability requirement.