Substn |
The substation for the given equipment. For lines, the substation shown will usually be the first alphanumeric substation name. (Ex. A line going from Alpha substation to Bravo substation would be listed under Alpha. aka, PJM EMS B1 field.) |
kV |
The voltage level for the given equipment expressed in kilovolts (kV). (aka, PJM EMS B2 field.) |
Dev |
Device name, abridged to a maximum of 8 characters, for the PJM EMS equipment device name for the given equipment. (aka, PJM EMS B3 field.) |
End |
PJM EMS END A or END B for a LINE, END A for a flow or series device or HIGH/LOW for a XFMR. |
Descr |
Description of the equipment. (aka, PJM EMS B3 Text field.) |
DLR |
Indicates if facility is enabled for dynamic ratings (Y) or not (N) |
Reason |
The reason for the ratings change. Available choices can be found in the Reasons for Rating Change text report. |
Start |
IF Active: Date and time the ratings were made effective.
IF Future: Estimated date and time the ratings will be in effect.
Date is in MM/DD/YYYY format. Time is in 24 hour format. |
Est. End |
Estimated date and time ratings are scheduled to end. The date is in the MM/DD/YYYY format. The time is in 24 hour format. |
Status |
The current status of the temporary rating request. The following statuses are displayed in the report: Active, Approved, and Awaiting Approval. |
Degf |
Temperature set in degrees Fahrenheit. |
Norm |
Continuous rating under Normal (NL) operating conditions. (See manual M-03: Section 2 re: Facility Ratings.) |
Long |
Long Term Emergency (LTE) rating. (See manual M-03: Section 2 re: Facility Ratings.) |
Shrt |
Short Term Emergency (STE) rating. (See manual M-03: Section 2 re: Facility Ratings.) |
Dump |
Load Dump (LD) emergency rating. (See manual M-03: Section 2 re: Facility Ratings.) |