Winter Storm Elliott Info
Winter Storm Elliott impacted the PJM region Dec. 23-25, 2022. This page is dedicated to providing information on the performance of PJM operations and markets during the storm, including PJM's preparations in advance of the event, emergency procedures implemented, generator performance, load forecast, and answers to frequently asked questions, including those related to the general calculation of Capacity Performance bonus payments and penalties.
PJM published the Winter Storm Elliott Event Analysis and Recommendation Report PDF on July 17, 2023.
On October 19, 2023, PJM posted a letter PDF to Members from Mike Bryson, Senior Vice President, Operations, affirming that PJM is preparing to implement recommendations from the FERC-NERC Joint Winter Storm Elliott Report and addressing an item on the upcoming Markets and Reliability Committee agenda.
Data Requests and Questions
Email PJM Customer Service
PAI Unit Specific Request Process
PJM Connect WEB | Login Instructions PDF
FERC Settlement Order Update
The Federal Energy Regulatory Commission approved an uncontested, comprehensive settlement package that resolves all complaints regarding non-performance charges arising from Winter Storm Elliott in December 2022. The approved settlement resulted from expedited talks requested by PJM in order to swiftly resolve the complaints.
At its Dec. 19 Open Meeting, the Commission approved PDF the settlement package between PJM and 81 other settling parties regarding non-performance charges assessed by PJM during Winter Storm Elliott.
Issue Tracking: Winter Storm Elliott
View information provided in the PJM stakeholder process meetings